Prepare for the General Contractor Exam with our comprehensive quiz. Featuring flashcards and multiple-choice questions, each accompanied by hints and detailed explanations, this resource will ensure you’re ready for your licensing examination!

Practice this question and more.


What is the maximum slope on the ground before a stepped foundation is required?

  1. 5%

  2. 10%

  3. 15%

  4. 20%

The correct answer is: 10%

The maximum slope that typically indicates the need for a stepped foundation is 10%. When the ground has a slope greater than this, it can lead to issues such as improper drainage, soil erosion, or structural instability for buildings. A stepped foundation helps to mitigate these challenges by providing a level base for construction, allowing for proper support and drainage while accommodating the elevation changes in the landscape. Building codes and best practices in construction often specify this 10% threshold because it is a critical point where more complex foundation solutions are necessary to ensure the long-term performance and safety of the structure. This principle is widely accepted in both residential and commercial construction as a standard guideline for managing sloped terrain efficiently.